729 Legacy Village Road SE

School Details:

Configuration: Grade 10 – Grade 12
Planned Opening: Fall 2018
Capacity: 1500
Sod Turning Celebration: Friday, September 18, 2015
Procurement Model: Designed, tendered and managed by CCSD

Construction Progress:

Funding announced: March 2014
Funding Received: October 2014
Fully Permitted, Design Complete, Tender Awarded: July 2016
Under Construction: July 2016
Anticipated Building Turnover: Data will be provided when milestone achieved
Projected Opening Date: Fall 2018

School Construction and Development Updates:

Principal Letter of Introduction
Please click the link below to see a letter from Mr. Mike Bolder, principal appointed to Legacy High School.
Principal Letter of Introduction

Principal Appointed to Legacy High School
Based upon the feedback received at the November 23 public consultation meeting and the School Administration Qualities, Attributes and Characteristics that was generated as a result of input at this meeting, the district has appointed a principal to the new Catholic high school under construction in Legacy. Click the link below to see the details of this appointment.
School Naming Letter
Principal Appointment Letter

Legacy High School Boundary Articulation
This public consultation process will include several meetings. A focus group consisting of representatives from school councils representing schools south of Fish Creek Park/130 Avenue S has been struck, and the work of this focus group will guide the district throughout the process. Please click the links below to see the presentations and Table Talk Feedback, Questions and Answers document from each of the public participation meetings as well as the final decision letter that was shared with the community.
Final Decision Letter
January 30 Table Talk Feedback, Questions & Answers
January 30 Presentation
November 23 Table Talk Feedback, Questions & Answers
November 23 Presentation

Legacy High School Administration Qualities, Attributes and Characteristics
At the public consultation session on November 23, 2016, participants developed the School Administration: Qualities, Attributes and Characteristics document. It will be used to assist in the appointment process of the School Principal and Administration.
School Administration: Qualities, Attributes and Characteristics

Legacy High School Information Fair (June 2015)
View full invitation
June 3 Presentation
June 3 Fact Sheet Handout

Information Meeting (January 2015)
Presentation
Feedback, Questions and Answers
Questions and Answers - received and answered as of February 27, 2015
School Selection Site Question
Questions Subsequent to March
High Schools Area Capacity Utilization
2016 – 2019 Capital Plan Summary

Philosophical Framework (June 2013 – November 2014)
The Philosophical Framework was developed based on extensive public consultation. It will guide the development and status of the new Legacy High School.
Philosophical Framework

Still to Come

  • Appointment of Principal: February 2017 (during or near the Principal staffing rounds)
  • School Naming Process/Committee: March 2017
  • Updates and Information: As required

School Design:

Click the link below to view a preliminary drawing of the street view and floor plans for the new school.
Preliminary Street View
First Floor Plan
Second Floor Plan

Photo Gallery:

Construction as of September 5, 2017:





Construction as of June 13, 2017:







Construction as of May 26, 2017:




Construction as of May 5, 2017:


Construction as of April 18, 2017:


Construction as of April 4, 2017:







Construction as of March 7, 2017:









Construction as of February 21, 2017:

Construction as of February 7, 2017:



Construction as of January 24, 2017:


Construction as of January 3, 2017:


Construction as of December 13, 2016:


Construction as of December 7, 2016:


Construction as of November 29, 2016:



Construction as of November 1, 2016:


Construction as of November 1, 2016:

Construction as of October 18, 2016:



Construction as of October 4, 2016:


Construction as of August 19, 2016:


S
eptember 2015 Sod Turning:

Legacy High School

729 Legacy Village Road SE

School Details:

Configuration: Grade 10 – Grade 12
Planned Opening: Fall 2018
Capacity: 1500
Sod Turning Celebration: Friday, September 18, 2015
Procurement Model: Designed, tendered and managed by CCSD

Construction Progress:

Funding announced: March 2014
Funding Received: October 2014
Fully Permitted, Design Complete, Tender Awarded: July 2016
Under Construction: July 2016
Anticipated Building Turnover: Data will be provided when milestone achieved
Projected Opening Date: Fall 2018

School Construction and Development Updates:

Principal Letter of Introduction
Please click the link below to see a letter from Mr. Mike Bolder, principal appointed to Legacy High School.
Principal Letter of Introduction

Principal Appointed to Legacy High School
Based upon the feedback received at the November 23 public consultation meeting and the School Administration Qualities, Attributes and Characteristics that was generated as a result of input at this meeting, the district has appointed a principal to the new Catholic high school under construction in Legacy. Click the link below to see the details of this appointment.
School Naming Letter
Principal Appointment Letter

Legacy High School Boundary Articulation
This public consultation process will include several meetings. A focus group consisting of representatives from school councils representing schools south of Fish Creek Park/130 Avenue S has been struck, and the work of this focus group will guide the district throughout the process. Please click the links below to see the presentations and Table Talk Feedback, Questions and Answers document from each of the public participation meetings as well as the final decision letter that was shared with the community.
Final Decision Letter
January 30 Table Talk Feedback, Questions & Answers
January 30 Presentation
November 23 Table Talk Feedback, Questions & Answers
November 23 Presentation

Legacy High School Administration Qualities, Attributes and Characteristics
At the public consultation session on November 23, 2016, participants developed the School Administration: Qualities, Attributes and Characteristics document. It will be used to assist in the appointment process of the School Principal and Administration.
School Administration: Qualities, Attributes and Characteristics

Legacy High School Information Fair (June 2015)
View full invitation
June 3 Presentation
June 3 Fact Sheet Handout

Information Meeting (January 2015)
Presentation
Feedback, Questions and Answers
Questions and Answers - received and answered as of February 27, 2015
School Selection Site Question
Questions Subsequent to March
High Schools Area Capacity Utilization
2016 – 2019 Capital Plan Summary

Philosophical Framework (June 2013 – November 2014)
The Philosophical Framework was developed based on extensive public consultation. It will guide the development and status of the new Legacy High School.
Philosophical Framework

Still to Come

  • Appointment of Principal: February 2017 (during or near the Principal staffing rounds)
  • School Naming Process/Committee: March 2017
  • Updates and Information: As required

School Design:

Click the link below to view a preliminary drawing of the street view and floor plans for the new school.
Preliminary Street View
First Floor Plan
Second Floor Plan

Photo Gallery:

Construction as of September 5, 2017:





Construction as of June 13, 2017:







Construction as of May 26, 2017:




Construction as of May 5, 2017:


Construction as of April 18, 2017:


Construction as of April 4, 2017:







Construction as of March 7, 2017:









Construction as of February 21, 2017:

Construction as of February 7, 2017:



Construction as of January 24, 2017:


Construction as of January 3, 2017:


Construction as of December 13, 2016:


Construction as of December 7, 2016:


Construction as of November 29, 2016:



Construction as of November 1, 2016:


Construction as of November 1, 2016:

Construction as of October 18, 2016:



Construction as of October 4, 2016:


Construction as of August 19, 2016:


S
eptember 2015 Sod Turning: