Prince of Peace opened September 2016 with students attending both Don Bosco & St. Gerard's to begin our school year. We were so excited to begin in our new school after the Thanksgiving weekend on Tuesday, October 11, 2016.

School Details:

Configuration: Kindergarten – Grade 9
Planned opening: Fall 2016
Capacity: 900 (including modulars)
Sod Turning Celebration: Friday, October 24, 2014
Procurement Model: Designed, tendered and managed by CCSD

Construction:

Funding announced: May 2013
Funding Received: October 2014
Fully Permitted, Design Complete, Tender Awarded: July 2015
Projected Opening Date: Fall 2016

October 2014 Sod Turning:

School History

Prince of Peace opened September 2016 with students attending both Don Bosco & St. Gerard's to begin our school year. We were so excited to begin in our new school after the Thanksgiving weekend on Tuesday, October 11, 2016.

School Details:

Configuration: Kindergarten – Grade 9
Planned opening: Fall 2016
Capacity: 900 (including modulars)
Sod Turning Celebration: Friday, October 24, 2014
Procurement Model: Designed, tendered and managed by CCSD

Construction:

Funding announced: May 2013
Funding Received: October 2014
Fully Permitted, Design Complete, Tender Awarded: July 2015
Projected Opening Date: Fall 2016

October 2014 Sod Turning: